Koroit township renewal - Stage 3

Share Koroit township renewal - Stage 3 on Facebook Share Koroit township renewal - Stage 3 on Twitter Share Koroit township renewal - Stage 3 on Linkedin Email Koroit township renewal - Stage 3 link

Works are set to commence on Stage 3 of the Koroit Township Renewal project with Stage 1 and Stage 2 works now completed.

Previous works stages consisted of new footpath, street furniture, drainage and general landscaping works completed on the northern side of Commercial Road between Station Street and Woolsthorpe Road.

Stage 3 works incorporate aesthetic and functional improvements to streetscapes and infrastructure in Commercial Road and High Street, Koroit.

Works in Commercial Road will be completed between High Street (Mickey Bourke's) and Commercial Place (Koroit Theatre).
Works will include:

  • Installation of new footpath
  • Construction of new driveways
  • Installation of new street furniture
  • Minor drainage works

Works in High Street will cover Commercial Road to Horne Avenue and include:

  • Drainage network upgrades
  • Installation of new concrete footpath
  • Road levelling, resealing and asphalting
  • Replacement of any existing street furniture
  • Replacement of current street trees
  • Provision of two new public bus stops close to the senior citizens and library and the northern end of High Street
  • Provision of a new school crossing at King Street

The project is being funding through a $2 million grant from the Federal Government’s Growing Regions program and matching funding from Moyne Shire Council.

Previous Township renewal project information


Engage Moyne Privacy Collection Notice

Works are set to commence on Stage 3 of the Koroit Township Renewal project with Stage 1 and Stage 2 works now completed.

Previous works stages consisted of new footpath, street furniture, drainage and general landscaping works completed on the northern side of Commercial Road between Station Street and Woolsthorpe Road.

Stage 3 works incorporate aesthetic and functional improvements to streetscapes and infrastructure in Commercial Road and High Street, Koroit.

Works in Commercial Road will be completed between High Street (Mickey Bourke's) and Commercial Place (Koroit Theatre).
Works will include:

  • Installation of new footpath
  • Construction of new driveways
  • Installation of new street furniture
  • Minor drainage works

Works in High Street will cover Commercial Road to Horne Avenue and include:

  • Drainage network upgrades
  • Installation of new concrete footpath
  • Road levelling, resealing and asphalting
  • Replacement of any existing street furniture
  • Replacement of current street trees
  • Provision of two new public bus stops close to the senior citizens and library and the northern end of High Street
  • Provision of a new school crossing at King Street

The project is being funding through a $2 million grant from the Federal Government’s Growing Regions program and matching funding from Moyne Shire Council.

Previous Township renewal project information


Engage Moyne Privacy Collection Notice

  • High Street works - tree replacement

    Share High Street works - tree replacement on Facebook Share High Street works - tree replacement on Twitter Share High Street works - tree replacement on Linkedin Email High Street works - tree replacement link

    Proposed tree replacement program - community poll

    Council is currently seeking community feedback on replacement tree species for the High Street component of Koroit Township Renewal Stage 3.

    The current planting of Metrosideros excelsa (New Zealand Christmas Trees) - between Commercial Road and the Mill Street area on both sides of the road will be removed. No other tree species will be removed as part of the works. The New Zealand Christmas Trees are being removed due to the following factors:

    • Construction requirements for upgrades to the drainage network and road works
    • The age and condition of these trees with a number showing senescence - ageing of the tree with a decline in function and vitality.
    • Impacts of the current root system on the drainage network and road condition both current and future.
    • Height of the trees that will require significant lopping to meet safety requirements associated with overhead powerlines.


    Replacement trees will be planted within the same locality of the current trees and formalised garden areas will be retained. Planned tree removal will occur late October.

    Council is proposing to plant one of the following species to maintain the current avenue presentation and is seeking resident feedback on a preferred species. Replacement tree work will include the installation of root barrier and irrigation.

    • Cercis chinensis - Chinese Redbud - Faerie Queen
    • Acer palmatum - Japanese Maple
    • Eucalyptus lansdowneana ssp albopurpurea - Purple Patch
    • Lagerstroemia indica - Crepe myrtle


    More details on the proposed species are provided in the 'Proposed tree species summary September 2025' in the High Street works section.

    You can vote for your preferred species by either:


    Voting will close on 10am, Monday 13 October. Results will be published online.

  • High Street works - updated layout plan

    Share High Street works - updated layout plan on Facebook Share High Street works - updated layout plan on Twitter Share High Street works - updated layout plan on Linkedin Email High Street works - updated layout plan link

    Moyne Shire Council are finalising design plans for upgrades to the footpath, road, drainage and landscaping in High Street from Commercial Road to Horne Street.

    Layout plans showing the main features of the works including landscaping, parking and new bus stops is now available to view in the documents section.

  • Footpath works to get underway

    Share Footpath works to get underway on Facebook Share Footpath works to get underway on Twitter Share Footpath works to get underway on Linkedin Email Footpath works to get underway link

    Commercial Road footpath works to get underway - Monday 6 October.

    Council is expecting footpath works to commence for Commercial Road Koroit on Monday 6 October with the project covering the southern side of Commercial Road from High St (Mickey Bourke's) to Commercial Place (Koroit Theatre).

    The first phase of works will start at the end of Mickey Bourke's building in High Street and work towards Commercial Road before paving work along the frontage of Mickey Bourke's gets underway. Traffic and pedestrian management controls will be put in place as works require, and all vehicles and pedestrians must follow directions and signage.

    During the High Street works phase, patrons to Mickey Bourke's will be able to enter off Commercial Road. Please note - there will be no parking available along the High Street areas of the works. Once works commence along the Commercial Road frontage of Mickey Bourke's, patrons will be able to enter off High Street.

    Phase 1 works will take until early to mid-December to complete and streetscape works will then pause for the summer school holidays.

    Phase 2 works will then start at the Koroit Theatre area in early February 2026.

    Council PMO officers will be regularly on site to oversee works and liaise with business owners, residents and visitors. Business owners, residents and visitors can also contact Council via email - pmo@moyne.vic.gov.au or via phone 1300 65 65 64.

    Landscape design plans for all the works completed and proposed for Commercial Road are available in the documents section of this project page.

    Questions relating to the project can also be posted through Q&A section on this project page.

  • Project update 12 September 2025

    Share Project update 12 September 2025 on Facebook Share Project update 12 September 2025 on Twitter Share Project update 12 September 2025 on Linkedin Email Project update 12 September 2025 link
    The first signs of works on the Koroit Streetscape Stage 3 project have started this week.
    Contractors have been onsite locating underground services on the south side of Commercial Road, Koroit in preparation for construction works to start in early October.
    In the coming days contractors will be locating underground services in High St between Commercial Rd and Horne St.

    Drainage works are planned to start late October early November.

Page last updated: 25 Sep 2025, 11:18 AM