Works update 1 October 2026
Streetscape and road improvement works will be undertaken along High Street, Koroit between Horne Street and Commercial Road. This stage of the project has been divided into three construction sections to minimise disruption and allow works to be completed efficiently.
Construction Sections
Works are scheduled to occur in October and November 2026, subject to weather conditions and contractor availability, between 7am to 6pm Monday to Friday, with the possibility of some weekend work. Estimated construction dates for each section are:
Section A: Horne Street to Mill Street - 5 October to 6 November 2026
Section B: Mill Street to King Street - 5 October to 6 November 2026
Section C: King Street to Commercial Road - 19 October to 27 November 2026
Important Information for Residents and Businesses
During construction working hours, the following traffic and access arrangements will apply:
- Sections of High Street will be closed to through traffic while roadworks are being undertaken, with detour routes to be signposted.
- Access for local residents, businesses, deliveries and emergency services will be maintained wherever practical.
- On-street parking will not be permitted within active work zones during construction activities.
- Traffic management, detours and reduced speed limits will be in place to ensure the safety of workers and road users.
- Pedestrian access will be maintained where possible, however some footpath closures may be required during specific stages of the works.
Victoria Park Access & Parking
During periods when works are occurring in Section B: Mill Street to King Street, access to Victoria Park will be maintained via the King Street entrance. Residents and visitors are asked to follow all temporary traffic signage and directions from traffic controllers.
During the Section B works no on-street parking will be permitted along the frontage of Victoria Park. Users are requested to park within Victoria Park and access via the King Street entrance.
Thank you
Council appreciates the patience and understanding of residents, businesses and visitors while these important improvements are undertaken. These works will enhance the safety, accessibility and appearance of High Street for the benefit of the community.