Gipps Street bridge replacement project
Moyne Shire Council is progressing the Gipps Street Bridge Replacement Project to deliver a safe, reliable and accessible crossing that meets current engineering, transport and flood resilience standards while supporting the long-term needs of the Port Fairy community.
Jointly funded through a $5 million Australian Government contribution and a $2.76 million Council investment, the project will replace the existing bridge with a modern structure that provides two-way vehicle access, improved pedestrian facilities, safer cycling connections and accommodation for critical water infrastructure.
Significant planning and preparatory work has been completed, including flood modelling, environmental and geotechnical assessments, stakeholder engagement, utility planning and approvals processes.
Following a competitive procurement process, contracts have now been awarded, marking a major milestone in the project’s delivery. Community feedback has helped shape the concept design and will continue to inform future project phases as Council progresses detailed design, construction planning and ongoing engagement with residents, businesses and stakeholders.
-
Project update February 2026
Share Project update February 2026 on Facebook Share Project update February 2026 on X (formerly Twitter) Share Project update February 2026 on Linkedin Email Project update February 2026 linkThe public tender process for the design and construct of the new Gipps Street Bridge in Port Fairy has now closed and officers are working through a detailed evaluation of the submissions received. This process follows Council's adopted Procurement Policy and Procedures.Further updates will be provided as we progress the tender process towards a design and construct contract.The bridge replacement project is being funded through a $5 million grant under the Federal Government’s Safer Local Roads and Infrastructure Program. The remaining $2.76 million of the $7.76 million project is being funded by Moyne Shire Council.A Community Reference Group has also been established with a wide range of community representatives selected from an Expression of Interest process that was promoted publicly in October last year.The purpose of the group is to:- Support transparent, ongoing engagement across the life of the project.- Enable sharing of community concerns, questions, and ideas.- Improve Council’s project communications.- Act as a conduit between Council and the broader community.The group's first meeting will be held on Monday 2 March 2026 and quarterly across the life of the project.Stay up to date on the Gipps Street bridge replacement project on this page at:The public tender process for the design and construct of the new Gipps Street Bridge in Port Fairy has now closed and officers are working through a detailed evaluation of the submissions received. This process follows Council's adopted Procurement Policy and Procedures.Further updates will be provided as we progress the tender process towards a design and construct contract.The bridge replacement project is being funded through a $5 million grant under the Federal Government’s Safer Local Roads and Infrastructure Program. The remaining $2.76 million of the $7.76 million project is being funded by Moyne Shire Council.A Community Reference Group has also been established with a wide range of community representatives selected from an Expression of Interest process that was promoted publicly in October last year.The purpose of the group is to:- Support transparent, ongoing engagement across the life of the project.- Enable sharing of community concerns, questions, and ideas.- Improve Council’s project communications.- Act as a conduit between Council and the broader community.The group's first meeting will be held on Monday 2 March 2026 and quarterly across the life of the project.Stay up to date on the Gipps Street bridge replacement project on this page at: -
Community feedback update
Share Community feedback update on Facebook Share Community feedback update on X (formerly Twitter) Share Community feedback update on Linkedin Email Community feedback update linkAs part of the Gipps Street Bridge Replacement project, Council recently sought community feedback on various aspects of the concept design for the new bridge through a community survey on Council’s Engage Moyne project page.
The survey attracted 120 responses with the majority (72%) being from Port Fairy residents and business operators.
Key responses for design features of the new bridge included:
- Opportunities to retain some of the bluestone features
- Looking at how the current design of the white pedestrian handrails can be incorporated into the design
- Keeping the overall design of the new bridge clean and simple
- Incorporating the proposed pedestrian viewing area with potentially seating and interpretive / information signage
- Lighting for pedestrian wayfinding – the type of lighting received a mix of responses from overhead bridge lighting, footpath downlighting, and in footpath uplighting. This will be investigated further as part of the detailed design phase.
The provision of bike lanes either on the bridge or as part of the pedestrian walkway with a mix of commentary on the need for safety for all users including pedestrians, cyclists, prams, strollers, and mobility equipment. Further assessment of bike lane treatments including regulations and optimum outcomes for all users will be undertaken as part of detailed design work.
There were some great ideas received on recognition of the history of the current bridge that was built in 1902. These included:
- Re-use of timbers for other projects or art works
- Document the history of the bridge and previous river crossings, and include any local stories about the bridge
- Information / interpretive signage / plaque
- Artist sketches or paintings, or a photographic record of the bridge
- Recognition of traditional owners – artwork, signage, naming
Commentary was also received around keeping the community informed about the bridge project, impacts during construction and timeframes. Council is committed to ensuring that regular and timely communications are provided. In addition, Council will be working with community project reference group as part of Council’s ongoing engagement across the life of the project. This will enable the sharing of ideas, community concerns and improve Council’s communications.
A summary of the community concept design feedback is provided in the project document library.
As part of the Gipps Street Bridge Replacement project, Council recently sought community feedback on various aspects of the concept design for the new bridge through a community survey on Council’s Engage Moyne project page.
The survey attracted 120 responses with the majority (72%) being from Port Fairy residents and business operators.
Key responses for design features of the new bridge included:
- Opportunities to retain some of the bluestone features
- Looking at how the current design of the white pedestrian handrails can be incorporated into the design
- Keeping the overall design of the new bridge clean and simple
- Incorporating the proposed pedestrian viewing area with potentially seating and interpretive / information signage
- Lighting for pedestrian wayfinding – the type of lighting received a mix of responses from overhead bridge lighting, footpath downlighting, and in footpath uplighting. This will be investigated further as part of the detailed design phase.
The provision of bike lanes either on the bridge or as part of the pedestrian walkway with a mix of commentary on the need for safety for all users including pedestrians, cyclists, prams, strollers, and mobility equipment. Further assessment of bike lane treatments including regulations and optimum outcomes for all users will be undertaken as part of detailed design work.
There were some great ideas received on recognition of the history of the current bridge that was built in 1902. These included:
- Re-use of timbers for other projects or art works
- Document the history of the bridge and previous river crossings, and include any local stories about the bridge
- Information / interpretive signage / plaque
- Artist sketches or paintings, or a photographic record of the bridge
- Recognition of traditional owners – artwork, signage, naming
Commentary was also received around keeping the community informed about the bridge project, impacts during construction and timeframes. Council is committed to ensuring that regular and timely communications are provided. In addition, Council will be working with community project reference group as part of Council’s ongoing engagement across the life of the project. This will enable the sharing of ideas, community concerns and improve Council’s communications.
A summary of the community concept design feedback is provided in the project document library.
-
Expression of Interest - Community Reference Group
Share Expression of Interest - Community Reference Group on Facebook Share Expression of Interest - Community Reference Group on X (formerly Twitter) Share Expression of Interest - Community Reference Group on Linkedin Email Expression of Interest - Community Reference Group linkCLOSED: This discussion has concluded.Council is seeking Expressions of Interest from local community members who would like to be part of the Gipps Street Bridge Community Reference Group.
The Reference Group will be part of Council's engagement program across the life of the project. It will enable the sharing of ideas, community concerns and questions, improve Council's communications and act as a contact point for Council and the wider community.
The Reference Group will comprise a Councillor representative and Council officers from the project team, and local business operators, service groups and residents. The Group will meet on a bi-monthly basis during the first phases of the project starting from February 2026. Any changes to meeting frequency once construction commences will be discussed and agreed with the Group. A terms of reference and supporting protocols will be provided to confirmed Group members.
Council will review all Expressions of Interest received and aim for a balance of age, representation, skills and interests.
Expressions of Interest have now closed.
Council is seeking Expressions of Interest from local community members who would like to be part of the Gipps Street Bridge Community Reference Group.
The Reference Group will be part of Council's engagement program across the life of the project. It will enable the sharing of ideas, community concerns and questions, improve Council's communications and act as a contact point for Council and the wider community.
The Reference Group will comprise a Councillor representative and Council officers from the project team, and local business operators, service groups and residents. The Group will meet on a bi-monthly basis during the first phases of the project starting from February 2026. Any changes to meeting frequency once construction commences will be discussed and agreed with the Group. A terms of reference and supporting protocols will be provided to confirmed Group members.
Council will review all Expressions of Interest received and aim for a balance of age, representation, skills and interests.
Expressions of Interest have now closed.
-
Environmental assessment underway
Share Environmental assessment underway on Facebook Share Environmental assessment underway on X (formerly Twitter) Share Environmental assessment underway on Linkedin Email Environmental assessment underway linkCouncil has appointed Aquatica Environmental to undertake terrestrial and aquatic environmental assessments of the works zone for the Gipps Street Bridge. Aquatica Environmental has undertaken a range of similar projects for major bridge and road projects along the Great Ocean Road and southern Victoria and brings professional and qualified expertise to this process.
Starting in late September, the Aquatica team will undertake:
- desktop and onsite assessments aquatic and terrestrial biodiversity, flora, fauna and estuarine habitats, including seasons considerations
- Identify ecologically significant area
- Identify potential direct and indirect impacts of the bridge project
- Identify any legislative and regulatory triggers
- Develop environmentalContinue reading
Council has appointed Aquatica Environmental to undertake terrestrial and aquatic environmental assessments of the works zone for the Gipps Street Bridge. Aquatica Environmental has undertaken a range of similar projects for major bridge and road projects along the Great Ocean Road and southern Victoria and brings professional and qualified expertise to this process.
Starting in late September, the Aquatica team will undertake:
- desktop and onsite assessments aquatic and terrestrial biodiversity, flora, fauna and estuarine habitats, including seasons considerations
- Identify ecologically significant area
- Identify potential direct and indirect impacts of the bridge project
- Identify any legislative and regulatory triggers
- Develop environmental management and mitigation measures for inclusion in the project Construction and Environmental Management Plan
- Develop an environment impacts and risk register.
The report and its findings will be considered and reviewed as part of ongoing works planning processes, with the final report due mid-November.
Moyne Shire Council would like to acknowledge the Federal Government $5 million funding contribution to the project through the Safer Local Roads and Infrastructure program.
-
Procurement plan
Gipps Street bridge replacement project has finished this stage -
Design and construct specifications
Gipps Street bridge replacement project has finished this stage -
Geotechnical investigation and Environmental assessment
Gipps Street bridge replacement project has finished this stage -
Design and construct tender period
Gipps Street bridge replacement project has finished this stage -
Tender evaluation presented to Council
Gipps Street bridge replacement project has finished this stage -
Contract finalisation
Gipps Street bridge replacement project has finished this stage -
Detailed design
Gipps Street bridge replacement project has finished this stage -
Finalise permits and approvals
Gipps Street bridge replacement project is currently at this stage -
Offsite fabrication and construction
this is an upcoming stage for Gipps Street bridge replacement project -
Onsite construction
this is an upcoming stage for Gipps Street bridge replacement project -
Roadworks, footpaths and works completion
this is an upcoming stage for Gipps Street bridge replacement project
- Is the bridge replacement project ahead, or behind schedule?
- How exactly is the project being funded?
- Who is the contractor that council has engaged for the works?
- Will Council be upgrading the intersection of Woodbine Road and the Princes Highway to improve safety?
- What factors will determine the start date?
- How will council keep the community informed about the project?
- What will happen when the current bridge is demolished?
- How will residents, visitors, school buses and emergency services access Griffiths Street when the bridge is closed?
- What plans are in place to deal with the bridge’s closure?
- Will there be ongoing community information sessions?
- What happens in the event of a critical incident on or near Griffiths Street?
- What will the replacement bridge look like?
- Will materials such as timber and stone from the old bridge be available for community or residents to use?
- What has been achieved to date?
- How long will it take to drive when the detour is in place?
- Will extra parking spaces be available close to the footbridge?
- How will the old bridge’s history be recognised?
- Will the demolition and construction of the new bridge impact the local environment?
- Is council planning to celebrate the new bridge’s opening with an event?
- What can people do if they have questions about the project?
-
Gipps Street Bridge Design Concepts.pdf (7.64 MB) (pdf)
-
FAQs Sept 2026.pdf (323 KB) (pdf)
-
Community feedback summary November 2025 (1.45 MB) (pdf)
-
Gipps St Bridge - CRG Agenda 1 and Presentation - 2 March 2026 (274 KB) (pdf)
-
Gipps St Bridge - CRG Minutes 1 - 2 March 2026 (208 KB) (pdf)
-
CRG Presentation 19 May 2026.pdf (2.46 MB) (pdf)
-
Gipps St Bridge - CRG 2 Agenda - 19 May 2026.pdf (209 KB) (pdf)
-
Gipps St Bridge - CRG 2 Minutes -19 May 2026.pdf (235 KB) (pdf)
-
Gipps St Bridge - CRG 3 Agenda and Presentation - 27 July 2026 (941 KB) (pdf)
-
Gipps St Bridge- CRG 3 Minutes - 27 July 2026 (273 KB) (pdf)
-
PM
Phone 1300 656 565 Email moyne@moyne.vic.gov.au