Gipps Street bridge replacement project
With the Federal Government's announcement of $5 million funding contribution from Safer Local Roads and Infrastructure Program, with a further $2.76 million from Moyne Shire to the project Council has developed a concept plan showing a representation of the style and design of the proposed new bridge in Port Fairy.
The concept is based on:
- Department of Transport statutory design and construction standards
- Independent flood modelling based on a number of different bridge designs including height, abutments and number of piers.
- Construction methodologies that consider the site, location, constraints and desired timeframes
- Provision of critical water assets for the town of Port Fairy that are currently connected to the existing bridge
- Provision of a safe pedestrian footpath and bike lanes as part of the new bridge
- Achievable and practical connections to the existing road and footpath network
- Ongoing maintenance and longer-term renewal management.
The concrete bridge has two piers, two-way vehicle access, a pedestrian footpath on the upstream side of the bridge to link in with the broader footpath network and options for either on-road or shared bicycle lanes.
Key tasks to deliver the project are listed in the project milestones. Council is currently forecasting construction commencement April 2027.
Further background to the project and updated condition reports and usability of the current bridge can be found on our Gipps Street Bridge Engage page.
Moyne Shire Council would like to acknowledge the Federal Government $5 million funding contribution to the project through the Safer Local Roads and Infrastructure program.
With the Federal Government's announcement of $5 million funding contribution from Safer Local Roads and Infrastructure Program, with a further $2.76 million from Moyne Shire to the project Council has developed a concept plan showing a representation of the style and design of the proposed new bridge in Port Fairy.
The concept is based on:
- Department of Transport statutory design and construction standards
- Independent flood modelling based on a number of different bridge designs including height, abutments and number of piers.
- Construction methodologies that consider the site, location, constraints and desired timeframes
- Provision of critical water assets for the town of Port Fairy that are currently connected to the existing bridge
- Provision of a safe pedestrian footpath and bike lanes as part of the new bridge
- Achievable and practical connections to the existing road and footpath network
- Ongoing maintenance and longer-term renewal management.
The concrete bridge has two piers, two-way vehicle access, a pedestrian footpath on the upstream side of the bridge to link in with the broader footpath network and options for either on-road or shared bicycle lanes.
Key tasks to deliver the project are listed in the project milestones. Council is currently forecasting construction commencement April 2027.
Further background to the project and updated condition reports and usability of the current bridge can be found on our Gipps Street Bridge Engage page.
Moyne Shire Council would like to acknowledge the Federal Government $5 million funding contribution to the project through the Safer Local Roads and Infrastructure program.
-
Community Reference Group meeting 2 March 2026
Share Community Reference Group meeting 2 March 2026 on Facebook Share Community Reference Group meeting 2 March 2026 on Twitter Share Community Reference Group meeting 2 March 2026 on Linkedin Email Community Reference Group meeting 2 March 2026 linkMoyne Shire Council held the first Gipps Street Bridge Community Reference Group meeting on 2 March 2026. Community representatives were selected from an Expressions of Interest process undertaken in October 2025. The Group is chaired by Mayor Cr Jordan Lockett with members of Council’s project management team also in attendance.
Please refer to Documents area of this page for:
- Meeting 2 March 2026 agenda and presentation
- Meeting 2 March 2026 minutesThe community is also welcome to continue to post questions about the project via the Q&A section on this page; via email to which Council will respond directly; or which can also be tabled at future Community Reference Group meetings.
The next meeting has been scheduled for 2pm, 11 May 2026.
Moyne Shire Council held the first Gipps Street Bridge Community Reference Group meeting on 2 March 2026. Community representatives were selected from an Expressions of Interest process undertaken in October 2025. The Group is chaired by Mayor Cr Jordan Lockett with members of Council’s project management team also in attendance.
Please refer to Documents area of this page for:
- Meeting 2 March 2026 agenda and presentation
- Meeting 2 March 2026 minutesThe community is also welcome to continue to post questions about the project via the Q&A section on this page; via email to which Council will respond directly; or which can also be tabled at future Community Reference Group meetings.
The next meeting has been scheduled for 2pm, 11 May 2026.
-
Project update February 2026
Share Project update February 2026 on Facebook Share Project update February 2026 on Twitter Share Project update February 2026 on Linkedin Email Project update February 2026 linkThe public tender process for the design and construct of the new Gipps Street Bridge in Port Fairy has now closed and officers are working through a detailed evaluation of the submissions received. This process follows Council's adopted Procurement Policy and Procedures.Further updates will be provided as we progress the tender process towards a design and construct contract.The bridge replacement project is being funded through a $5 million grant under the Federal Government’s Safer Local Roads and Infrastructure Program. The remaining $2.76 million of the $7.76 million project is being funded by Moyne Shire Council.A Community Reference Group has also been established with a wide range of community representatives selected from an Expression of Interest process that was promoted publicly in October last year.The purpose of the group is to:- Support transparent, ongoing engagement across the life of the project.- Enable sharing of community concerns, questions, and ideas.- Improve Council’s project communications.- Act as a conduit between Council and the broader community.The group's first meeting will be held on Monday 2 March 2026 and quarterly across the life of the project.Stay up to date on the Gipps Street bridge replacement project on this page at:The public tender process for the design and construct of the new Gipps Street Bridge in Port Fairy has now closed and officers are working through a detailed evaluation of the submissions received. This process follows Council's adopted Procurement Policy and Procedures.Further updates will be provided as we progress the tender process towards a design and construct contract.The bridge replacement project is being funded through a $5 million grant under the Federal Government’s Safer Local Roads and Infrastructure Program. The remaining $2.76 million of the $7.76 million project is being funded by Moyne Shire Council.A Community Reference Group has also been established with a wide range of community representatives selected from an Expression of Interest process that was promoted publicly in October last year.The purpose of the group is to:- Support transparent, ongoing engagement across the life of the project.- Enable sharing of community concerns, questions, and ideas.- Improve Council’s project communications.- Act as a conduit between Council and the broader community.The group's first meeting will be held on Monday 2 March 2026 and quarterly across the life of the project.Stay up to date on the Gipps Street bridge replacement project on this page at: -
Community feedback update
Share Community feedback update on Facebook Share Community feedback update on Twitter Share Community feedback update on Linkedin Email Community feedback update linkAs part of the Gipps Street Bridge Replacement project, Council recently sought community feedback on various aspects of the concept design for the new bridge through a community survey on Council’s Engage Moyne project page.
The survey attracted 120 responses with the majority (72%) being from Port Fairy residents and business operators.
Key responses for design features of the new bridge included:
- Opportunities to retain some of the bluestone features
- Looking at how the current design of the white pedestrian handrails can be incorporated into the design
- Keeping the overall design of the new bridge clean and simple
- Incorporating the proposed pedestrian viewing area with potentially seating and interpretive / information signage
- Lighting for pedestrian wayfinding – the type of lighting received a mix of responses from overhead bridge lighting, footpath downlighting, and in footpath uplighting. This will be investigated further as part of the detailed design phase.
The provision of bike lanes either on the bridge or as part of the pedestrian walkway with a mix of commentary on the need for safety for all users including pedestrians, cyclists, prams, strollers, and mobility equipment. Further assessment of bike lane treatments including regulations and optimum outcomes for all users will be undertaken as part of detailed design work.
There were some great ideas received on recognition of the history of the current bridge that was built in 1902. These included:
- Re-use of timbers for other projects or art works
- Document the history of the bridge and previous river crossings, and include any local stories about the bridge
- Information / interpretive signage / plaque
- Artist sketches or paintings, or a photographic record of the bridge
- Recognition of traditional owners – artwork, signage, naming
Commentary was also received around keeping the community informed about the bridge project, impacts during construction and timeframes. Council is committed to ensuring that regular and timely communications are provided. In addition, Council will be working with community project reference group as part of Council’s ongoing engagement across the life of the project. This will enable the sharing of ideas, community concerns and improve Council’s communications.
A summary of the community concept design feedback is provided in the project document library.
As part of the Gipps Street Bridge Replacement project, Council recently sought community feedback on various aspects of the concept design for the new bridge through a community survey on Council’s Engage Moyne project page.
The survey attracted 120 responses with the majority (72%) being from Port Fairy residents and business operators.
Key responses for design features of the new bridge included:
- Opportunities to retain some of the bluestone features
- Looking at how the current design of the white pedestrian handrails can be incorporated into the design
- Keeping the overall design of the new bridge clean and simple
- Incorporating the proposed pedestrian viewing area with potentially seating and interpretive / information signage
- Lighting for pedestrian wayfinding – the type of lighting received a mix of responses from overhead bridge lighting, footpath downlighting, and in footpath uplighting. This will be investigated further as part of the detailed design phase.
The provision of bike lanes either on the bridge or as part of the pedestrian walkway with a mix of commentary on the need for safety for all users including pedestrians, cyclists, prams, strollers, and mobility equipment. Further assessment of bike lane treatments including regulations and optimum outcomes for all users will be undertaken as part of detailed design work.
There were some great ideas received on recognition of the history of the current bridge that was built in 1902. These included:
- Re-use of timbers for other projects or art works
- Document the history of the bridge and previous river crossings, and include any local stories about the bridge
- Information / interpretive signage / plaque
- Artist sketches or paintings, or a photographic record of the bridge
- Recognition of traditional owners – artwork, signage, naming
Commentary was also received around keeping the community informed about the bridge project, impacts during construction and timeframes. Council is committed to ensuring that regular and timely communications are provided. In addition, Council will be working with community project reference group as part of Council’s ongoing engagement across the life of the project. This will enable the sharing of ideas, community concerns and improve Council’s communications.
A summary of the community concept design feedback is provided in the project document library.
-
Expression of Interest - Community Reference Group
Share Expression of Interest - Community Reference Group on Facebook Share Expression of Interest - Community Reference Group on Twitter Share Expression of Interest - Community Reference Group on Linkedin Email Expression of Interest - Community Reference Group linkCLOSED: This discussion has concluded.Council is seeking Expressions of Interest from local community members who would like to be part of the Gipps Street Bridge Community Reference Group.
The Reference Group will be part of Council's engagement program across the life of the project. It will enable the sharing of ideas, community concerns and questions, improve Council's communications and act as a contact point for Council and the wider community.
The Reference Group will comprise a Councillor representative and Council officers from the project team, and local business operators, service groups and residents. The Group will meet on a bi-monthly basis during the first phases of the project starting from February 2026. Any changes to meeting frequency once construction commences will be discussed and agreed with the Group. A terms of reference and supporting protocols will be provided to confirmed Group members.
Council will review all Expressions of Interest received and aim for a balance of age, representation, skills and interests.
Expressions of Interest have now closed.
Council is seeking Expressions of Interest from local community members who would like to be part of the Gipps Street Bridge Community Reference Group.
The Reference Group will be part of Council's engagement program across the life of the project. It will enable the sharing of ideas, community concerns and questions, improve Council's communications and act as a contact point for Council and the wider community.
The Reference Group will comprise a Councillor representative and Council officers from the project team, and local business operators, service groups and residents. The Group will meet on a bi-monthly basis during the first phases of the project starting from February 2026. Any changes to meeting frequency once construction commences will be discussed and agreed with the Group. A terms of reference and supporting protocols will be provided to confirmed Group members.
Council will review all Expressions of Interest received and aim for a balance of age, representation, skills and interests.
Expressions of Interest have now closed.
-
Environmental assessment underway
Share Environmental assessment underway on Facebook Share Environmental assessment underway on Twitter Share Environmental assessment underway on Linkedin Email Environmental assessment underway linkCouncil has appointed Aquatica Environmental to undertake terrestrial and aquatic environmental assessments of the works zone for the Gipps Street Bridge. Aquatica Environmental has undertaken a range of similar projects for major bridge and road projects along the Great Ocean Road and southern Victoria and brings professional and qualified expertise to this process.
Starting in late September, the Aquatica team will undertake:
- desktop and onsite assessments aquatic and terrestrial biodiversity, flora, fauna and estuarine habitats, including seasons considerations
- Identify ecologically significant area
- Identify potential direct and indirect impacts of the bridge project
- Identify any legislative and regulatory triggers
- Develop environmentalContinue reading
Council has appointed Aquatica Environmental to undertake terrestrial and aquatic environmental assessments of the works zone for the Gipps Street Bridge. Aquatica Environmental has undertaken a range of similar projects for major bridge and road projects along the Great Ocean Road and southern Victoria and brings professional and qualified expertise to this process.
Starting in late September, the Aquatica team will undertake:
- desktop and onsite assessments aquatic and terrestrial biodiversity, flora, fauna and estuarine habitats, including seasons considerations
- Identify ecologically significant area
- Identify potential direct and indirect impacts of the bridge project
- Identify any legislative and regulatory triggers
- Develop environmental management and mitigation measures for inclusion in the project Construction and Environmental Management Plan
- Develop an environment impacts and risk register.
The report and its findings will be considered and reviewed as part of ongoing works planning processes, with the final report due mid-November.
Moyne Shire Council would like to acknowledge the Federal Government $5 million funding contribution to the project through the Safer Local Roads and Infrastructure program.
FAQs
- Why is the bridge being replaced?
- What does the overall project look like?
- How is the project being funded?
- Who is managing the project?
- What project planning activities has Council undertaken so far?
- What will the replacement bridge look like?
- What are the timelines for the project?
- What will happen when the current bridge is demolished?
- How will Council keep the community informed about the project?
Project milestones
-
Procurement plan
Gipps Street bridge replacement project has finished this stage -
Design and construct specifications
Gipps Street bridge replacement project has finished this stage -
Geotechnical investigation and Environmental assessment
Gipps Street bridge replacement project has finished this stage -
Design and construct tender period
Gipps Street bridge replacement project is currently at this stage -
Tender evaluation presented to Council
this is an upcoming stage for Gipps Street bridge replacement project -
Detailed design
this is an upcoming stage for Gipps Street bridge replacement project -
Finalise permits and approvals
this is an upcoming stage for Gipps Street bridge replacement project -
Offsite fabrication and construction
this is an upcoming stage for Gipps Street bridge replacement project -
Onsite construction
this is an upcoming stage for Gipps Street bridge replacement project -
Roadworks, footpaths and works completion
this is an upcoming stage for Gipps Street bridge replacement project
Follow Project
Who's Listening
-
PM
Phone 1300 656 565 Email moyne@moyne.vic.gov.au



