Asphalting works will commence along High Street, Koroit between Commercial Road and Horne Street from Monday 16 November 2026.

Works are planned in the following sections but may be subject to change due to weather and other circumstances.

  • Monday – Commercial Road to Council depot
  • Tuesday – Council Depot to Victoria Park
  • Wednesday – Victoria Park to medical centre/kinder
  • Thursday – medical centre/kinder to Horne Street

During construction working hours, the following traffic and access arrangements will apply:

  • Works will occur between 7:30am to 6pm
  • Sections planned for Asphalting will be closed to through traffic while works are being undertaken, with detour routes clearly signposted.
  • Access for residents, businesses, deliveries, and emergency services will be maintained wherever practical.
  • On-street parking will not be permitted during works.
  • Pedestrian access will be maintained where possible.

Council appreciates the patience and understanding of residents, businesses, and visitors while these important improvements are undertaken.