The construction of the new Gipps Street Bridge Port Fairy is planned to begin in mid-March 2027, following the Port Fairy Folk Festival.

Construction is expected to take around 7-8 months and the river crossing will be fully closed to vehicles during the period.

Mayor Cr Jordan Lockett said the timelines were subject to final approvals and come after extensive consultation with community, Emergency Services and the Folk Festival Committee.

“The project team have been working flat-out to get all key elements lined up, ensuring as much as possible is considered to help the closure to be manageable for those it will affect,” he said.

“We know it is going to be a major inconvenience, but the closure is unavoidable and we are doing everything we can to try and limit the impacts.”

He said the Draft Bridge Closure Management plan was now out for community feedback and outlines steps council will take during the closure period.

“That plan takes everything we have heard from residents, businesses and our key stakeholders like emergency services and event organisers about the impacts the closure will have and how we can best manage those,” Cr Lockett said.

“I encourage everyone to have a look at that plan and see if there is anything we haven’t thought of that needs to be included – the community who use the bridge everyday are the best people to tell us what is needed.

“Our team have done a power of work behind the scenes to get us to this point, and they are now stepping up another gear as we move towards construction. This is a critical project for Port Fairy and one I think everyone agrees needs to happen.”

Cr Lockett said Council and its contractor Murray Construction will be working hard to minimise the closure period.

“We’ll be making the most of every opportunity we have to get ahead and look at every chance to get the bridge open earlier, but it’s going to depend on so many factors including the weather and river conditions.”

The Draft Bridge Closure Management Plan can be viewed here or at the Port Fairy Council Office and Visitor Information Centre.

Feedback can be provided online by clicking here or via a hard copy survey available at the Council office or Visitor Information Centre until November 23.

Share Bridge closure to begin after Folk Festival on Facebook Share Bridge closure to begin after Folk Festival on X (formerly Twitter) Share Bridge closure to begin after Folk Festival on Linkedin Email Bridge closure to begin after Folk Festival link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>