Works underway
Works in Wishart Street are now underway.
Tree removal began on July 18, with civil works to follow.
Summary staging of works will be as follows (dependent on weather)
- Drainage by end of August
- West side and east side kerbing by end of September
- Road works and resurfacing by end of October
- Landscaping and tree replanting with Queensland Box (3m height)
- Linemarking by end of October.