Construction is underway, get ready to play!
Construction has begun on the Macarthur Precinct Splash Pad and is on track to be completed in time for some summer fun!
Works completed so far include;
- Pipe work laid and concrete poured
- Installation of first splash pad elements
- Installation of boulders and garden
Works scheduled for the next two weeks;
- Electrical and plumbing works
- Install remaining splash pad elements
- Completion of pool and splash pad fencing
- Site earthworks; drainage pipes, pits and sub-surface irrigation