Works update

Works on the IGA to Woolsthorpe Road footpath works are well underway. Over the past couple weeks works have included:

▪ Repairs to existing bluestone kerbing

▪ Construction of charcoal coloured kerb tray

▪ Installation of three new coloured concrete driveways.

These works will continue over the next couple of weeks with paving works expected to start at the eastern end of the site in late February.

Parking bays are being temporarily reinstated as works progress along Commercial Road. Permanent reinstatement will occur as paving works are completed.